Project control using S Curve in provision of pedestal crane at PT. Medco E&P Natuna - West Belut Platform

Authors

DOI:

https://doi.org/10.55942/pssj.v5i8.489

Keywords:

Construction, pedestal crane, project managements, s curves, time schedule

Abstract

In the implementation of a project, three main aspects are indicators of the success of the project: cost, schedule, and quality. If the cost and time of project implementation are in accordance with the planning and quality requirements, then the project can be said to be successful. Time plays a significant role in construction management projects, where time is also a management function. With good and proper time control, obstacles to delays in project implementation can be avoided as much as possible. The purpose of this study was to determine the cause of the achievement or deviation of work between the realization in the field and the planned time schedule for the procurement of a pedestal crane unit for a new platform in the operational area of ​​ block-B-Natuna.

Author Biographies

Rahmat Rahmat, Universitas Sains Indonesia

Rahmat is affiliated with the University of Science Indonesia, Indonesia, where he plays a leading role in construction project management and mechanical engineering. With a strong background in materials and project management, his work focuses on the implementation and management of construction project management systems to support the quality of oil and gas projects and operational efficiency in the project environment. He is particularly interested in leveraging technology to improve work schedule efficiency in the implementation of oil and gas construction projects.

Dean Anggara Putra, Universitas Sains Indonesia

Dean Anggara Putra is a practitioner working in the field of glass materials as a designer. His research interests lie in manufacturing design. He has co-authored publications in national journals, contributing to the understanding of materials and manufacturing

Rifo Nurlaksana Restu, Universitas Sains Indonesia

Rifo Nurlaksana Restu is a practitioner working in the field of motor vehicle manufacturing. His research interests lie in manufacturing and production. He has co-authored publications in national journals, contributing to the understanding of two-wheeled motor vehicle manufacturing and production.

Jefri Imron, Universitas Sains Indonesia

Jefri Imron is a practitioner working in the management consulting field. His research interests lie in energy conversion and occupational health and safety. He has co-authored publications in national journals, contributing to the understanding of occupational safety and energy conversion. He is currently pursuing a doctoral degree at a state university in Indonesia.

Marhaendra Natawibawa, Universitas Sains Indonesia

Marhaendra Natawibawa is a practitioner working in the field of management consulting. His research interests lie in energy conversion and green energy. He has co-authored publications in national journals, contributing to the understanding of energy conversion and energy efficiency. He is currently pursuing a doctoral degree at a university in Indonesia.

Hery Sumardiyanto, Universitas Sains Indonesia

Hery Sumardiyanto is a practitioner working in the field of motor vehicle manufacturing. His research interests lie in manufacturing and supply chain. He has co-authored publications in national journals, contributing to the understanding of two-wheeled motor vehicle manufacturing and supply chain. He is currently pursuing a doctoral degree at a university in Indonesia.

Khairil Munawar, Universitas Sains Indonesia

Khairil Munawar is a practitioner working in the fields of AI and big data. His research interests lie in automation. He has co-authored publications in national journals, contributing to the understanding of artificial intelligence and big data.

Thomas Junaedi, Universitas Sains Indonesia

Thomas Junaedi is affiliated with the Indonesian University of Science, Indonesia, where he plays a leading role in manufacturing and materials. He also is a practitioner working in the field of production and manufacture motor vehicle. He is particularly interested in the use of materials and composites to improve material strength. He is currently pursuing a doctoral degree at a university in Malaysia.

References

Abdillah, G. S., Waluyo, M., Teknik, F., Gunung, M., Surabaya, A., Surabaya, K., Teknik, F., Gunung, M., Surabaya, A., & Surabaya, K. (2025). Jurnal Hasi Penelitian Dan Pengkajian Ilmiah Eksakta. 04(01), 8–13.

Agnes Maria Wijaya. (2015). Monitoring Penjadwalan Proyek & Evaluasi Jumlah Tower Crane Pada Proyek Condominium & Podium Sebuah Plaza Di Tengah Kota. 4(2), 1–6.

Al-bab, U., & Hepiyanto, R. (2024). Analisa Manajemen Waktu Pekerjaan Renovasi Pembangunan Cafe Terakota. Jurnal Talenta Sipil, 7(1), 142. https://doi.org/10.33087/talentasipil.v7i1.400

Amani, W., Helmi, & Irawan, B. (2012). Perbandingan Aplikasi CPM, PDM, dan Teknik Bar Chart- Kurva S Pada Optimalisasi Penjadwalan Proyek. Buletin Ilmiah Math. Stat. Dan Terapannya (Bimaster), 01(1), 15–22. https://jurnal.untan.ac.id/index.php/jbmstr/article/view/604/623

Anton, S., Kusumastuti, D. I., & Kunci, K. (2024). Evaluasi Kinerja Pembangunan Ruang Praktik Siswa Menggunakan Kurva-S dan. 10(2), 146–159.

Brianorman, Y. (2019). JEPIN (Jurnal Edukasi dan Penelitian Informatika) Sistem Informasi Monitoring dan Evaluasi dengan Menggunakan Kurva S sebagai Indikator Realisasi dan Kemajuan Pekerjaan. Sistem Informasi Monitoring Dan Evaluasi Dengan Menggunakan Kurva S Sebagai Indikator Realisasi Dan Kemajuan Pekerjaan, 5(3), 344–351.

Hardianta, C., & Effendy, M. (2021). Penjadwalan Proyek Dengan Kurva S Berbasis Tenaga Kerja Pada Proyek Pembangunan Perumahan. Seminar Keinsinyuran Program Studi Program Profesi Insinyur, 1(2), 565–572. https://doi.org/10.22219/skpsppi.v2i1.4434

Husen, A. (2011). lr. Abrar Husen, MT. Manajemen Proyek: Perencanaan, Penjadwalan, & Pengendalian Proyek, 2(1), 1–143.

Imron, Jefri, R. R., Teknik, F., & Indonesia, S. (2025). Analisis Desain dan Keandalan Bejana Bertekanan pada Industri Energi Pendekatan Numerik dan Eksperimental. Jurnal Ekselenta-Jurnal Ilmiah Fakultas Teknik, 1(2), 1–10.

Konior, J., & Szóstak, M. (2020). The S-curve as a tool for planning and controlling of construction process-case study. Applied Sciences (Switzerland), 10(6). https://doi.org/10.3390/app10062071

Miftah Fauza, N. kartika. (2020). Metode Earned Value Pada Proyek Pembangunan Trotoar Kegiatan umum proyek dapat diartikan sebagai kegiatan sementara yang berlangsung dengan jangka wakt terbatas dan dikelola satu atau lebih organisasi agar proyek . Hal ini agar dapat mendeteksi sedini mau. Jurnal Ilmiah SANTIKA, 10(1), 37–48.

Munasir, U. F., & Renaningsih, R. (2023). Manajemen Waktu pada Struktur Bawah Proyek Pembangunan Rumah Sakit Kasih Ibu Surakarta. Prosiding Seminar Nasional …. https://proceedings.ums.ac.id/index.php/sipil/article/view/2783%0Ahttps://proceedings.ums.ac.id/index.php/sipil/article/download/2783/2746

Rahmat. (2024a). Rancang bangun mesin stirling tipe gamma menggunakan metode vdi 2221. Ekselenta, Jurnal, 1(1), 1–9.

Rahmat. (2025). Evaluasi Keterlambatan Jadwal Pelaksanaan Proyek Konstruksi Pengadaan Pedestal Crane PT. XYZ. Ekselenta, Jurnal, 1(2), 6–13. https://doi.org/DOI: 10.13140/RG.2.2.16009.15202

Rahmat, & Isdaryanto Iskandar. (2023). Analisa keretakan material mounting boom hydrolic axcavator merk hitachi ZX-470 LC-3f di PT. Darma Henwa Tbk tambang Asam-asam Kalimantan Selatan. Jurnal TESLINK : Teknik Sipil Dan Lingkungan, 4(2), 124–136. https://doi.org/10.52005/teslink.v4i2.129

Rahmat, R. (2019). Pengembangan Mesin Stirling Tipe Gamma Sebagai Tenaga Penggerak Kipas Angin. Teknobiz : Jurnal Ilmiah Program Studi Magister Teknik Mesin, 9(1), 28–36. https://doi.org/10.35814/teknobiz.v9i1.887

Rahmat, R. (2024b). Analisa Kinerja Mesin T-101 Dan TM-660 Pada Proses Mock Up Hot Tapping Pipa LNG. Ekselenta, Jurnal, 1(1), 57–63. https://doi.org/DOI: 10.13140/RG.2.2.19364.59522

Sabariah, I., Syaiful, S., & Ida Hayati, N. (2020). Analisis Metode Network Planning Dan S-Curve Proyek Konstruksi Di Bogor. Astonjadro, 1(1), 28. https://doi.org/10.32832/astonjadro.v1i1.782

Soplanit Nony, Maelissa Nelda, & Henriette D. Titaley. (2021). Analisis Penerapan Metode Line of Balance Pada Pembangunan Rumah Susun Pemkab Kepulauan Tanimbar. Jurnal Simetrik, 11(2), 474–479.

Sugiyarto, Putra, D. D. A., & Purwanto, E. (2016). Penjadwalan Waktu Dan Sumber Daya Manusia Proyek Showroom Dan Bengkel Nissan Magelang. Matriks Teknik Sipil, 366–373.

Sukindrawati, B., Kartika, W., & Sarju, S. (2023). Evaluasi Kinerja Waktu Dengan Metode Konsep Nilai Hasil. Menara: Jurnal Teknik Sipil, 18(2), 110–114. https://doi.org/10.21009/jmenara.v18i2.36648

Sutopo, G. I., & Hendarti, L. (2022). Analisis Kurva S untuk Monitoring Pelaksanaan Proyek (Studi Kasus Proyek Rumah Tinggal di Jalan Cocak II nomer 3, Surakarta). Jurnal Scer, 32–48. https://ejurnal.unsa.ac.id/index.php/scer/article/view/11

Downloads

Published

2025-08-12

How to Cite

Rahmat, R., Putra, D. A., Restu, R. N., Imron, J., Natawibawa, M., Sumardiyanto, H., Munawar, K., & Junaedi, T. (2025). Project control using S Curve in provision of pedestal crane at PT. Medco E&P Natuna - West Belut Platform. Priviet Social Sciences Journal, 5(8), 115–124. https://doi.org/10.55942/pssj.v5i8.489

Issue

Section

Articles
Abstract Views: 37 | File Views: 29